OUR ADU PROCESS
Excavated foundation footings and installed underground sewer lines to prepare for structural and utility integration.
Constructed foundation forms and applied a vapor barrier for moisture protection and code compliance.
Installed rebar and anchor bolts to the foundation (City inspection to follow)
Once the foundation passed city inspection, we poured concrete for a strong, level slab.
Removed formwork, cleaned the slab, and staged materials for vertical framing.
Exterior walls framed, establishing the layout and structural outline of the new addition.
Interior framing is complete and roof trusses are nearly finished, defining internal spaces.
Installed roof fascia and shear walls for structural integrity. Rough plumbing, electrical, and gas lines are now in place.